Back in May 2010
, I posted an article entitled
Effort Estimation in Agile Software Development - Applying the Pert Weighted Average formula, which has been one of the most popular articles on this blog.
Amongst the feedback received there were many requests asking me to provide more details on how to devise the numbers to apply on the formula. This article expands on the topic by explaining my way of coming up with the numbers for the
optimistic, pessimistic and realistic components of the Pert Weighted Average formula.
As explained
here, the I use the following formula to estimate the duration to develop each user story that make up an iteration:
(Optimistic + (4 * Realistic) + Pessimistic) / 6 .
How to apply the formula
Optimistic - I ask each developer to provide me with an estimation of how long it will take to complete each story they will work on. This is the number that I use for the optimistic component.
To estimate the other components of the formula I use a combination of grading user stories by size and complexity as outlined in the first article. However it is not as simple as that.
I don't see estimation as an exact science and therefore blindly applying a formula will not work under all circumstances. However, the formula does provide me with a consistent estimation procedure that has worked for at least 10 years now.
Another variable that I use in estimating the development effort is my team's velocity. I have a detailed record of the team's velocity recorded against functionality deployed to production. This helps me to compare actual duration of completed user stories against the effort that was originally estimated and use it as a basis to estimate the effort to develop stories that are similar in size and complexity ratings.
So here is how I devise the numbers for the rest of the formula.
Realistic - I search TFS (Team Foundation Server) for completed stories with similar size and complexity ratings and take the actual time that it took to develop it as the realistic component of the formula.
Pessimistic - It is hard to estimate what a pessimistic duration would be because of many different variables that come into play such as risks associated with the particular piece of functionality, complexity, developer experience and many other variables. I have met some development managers that double the duration estimated as the realistic and use it as the pessimistic. I don't blindly assign a number to it, I try to take everything into consideration in order to come up with an estimation that makes sense.
I don't think that there is a formula that you can blindly take to estimate software development effort. It is not as simple as that as there are many components that come into play in effort estimation, project management and software development.
No comments:
Post a Comment